(1) Be able to manually enter the hours which were worked on a particular task as the hours are completed, and get an accurate picture of how long (how many hours) a task took.
You can use the task usage view, I prefer to use the Gantt view in the top pane and the task usage view in the bottom pane.
If you right click in the right hand side of the task usage view you can change the information to "work" and "actual work".
Expand the timescale to the relevent extent and you can manually put the hours in.
If you make the task "Fixed Work" than the duration will change accordingly.
(2) I ideally I would like to have another column in which I stated the anticipated time a task was expected to take and then subtract the time taken from the anticipated time and get an idea as to the over or under on the task.
The baseline lends itself to this, if you save a baseline it will save the work and duration as well as start, finish and cost.
The column you will need will be "Duration variance", the difference between baseline and current planned or actual.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
(1) Be able to manually enter the hours which were worked on a particular task as the hours are completed, and get an accurate picture of how long (how many hours) a task took.
You can use the task usage view, I prefer to use the Gantt view in the top pane and the task usage view in the bottom pane.
If you right click in the right hand side of the task usage view you can change the information to "work" and "actual work".
Expand the timescale to the relevent extent and you can manually put the hours in.
If you make the task "Fixed Work" than the duration will change accordingly.
(2) I ideally I would like to have another column in which I stated the anticipated time a task was expected to take and then subtract the time taken from the anticipated time and get an idea as to the over or under on the task.
The baseline lends itself to this, if you save a baseline it will save the work and duration as well as start, finish and cost.
The column you will need will be "Duration variance", the difference between baseline and current planned or actual.
Hope this helps,
Will