You dont need to do for each month seperately, it will show automatically. If you feel any problem then just select all date( not day) of month and click default button.You can check for other months.
I am using MSP version 2000 and it is working even though if select any specific day as non working day that also shows in bar area as band of non working day. I think it works in lower version of MSP also.
Select Thu & Fri then make them non default working time and Sat & Sun as non working time in calander.This will change weekend as Thu & Fri as you want it.
There is no levelled non working day band in MSP. You can edit the day you want non working that will show in bar area then you insert the text (reason of non working day) on the band. Hope this will help you to identify non working day.
I have similar problem in showing the week-ends to Thu/Fri as the gray band is fixed to Sat/Sun. Note that Thu/Fri is the week-end in Arabic countries.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Thanks gents I now understand that this is not possible.
Thanks Raj, youve been very helpful.
You dont need to do for each month seperately, it will show automatically. If you feel any problem then just select all date( not day) of month and click default button.You can check for other months.
Raj,
Do I need to do that for all the 36 months of the project duration? Is there no automatic way?
I am using MSP version 2000 and it is working even though if select any specific day as non working day that also shows in bar area as band of non working day. I think it works in lower version of MSP also.
Raj,
But still the gray band in the graphics wont move to Thu/Fri. BTW, which version are you using?
Select Thu & Fri then make them non default working time and Sat & Sun as non working time in calander.This will change weekend as Thu & Fri as you want it.
There is no levelled non working day band in MSP. You can edit the day you want non working that will show in bar area then you insert the text (reason of non working day) on the band. Hope this will help you to identify non working day.
I have similar problem in showing the week-ends to Thu/Fri as the gray band is fixed to Sat/Sun. Note that Thu/Fri is the week-end in Arabic countries.
proj_planner