MS Project Calendar Mods

F
Forum Guest 👤 Member for 17 years 4 months
R
Raj Maurya 👤 Member for 21 years 10 months

You don’t need to do for each month seperately, it will show automatically. If you feel any problem then just select all date( not day) of month and click default button.You can check for other months.

F
Forum Guest 👤 Member for 17 years 4 months

Raj,



Do I need to do that for all the 36 months of the project duration? Is there no automatic way?

R
Raj Maurya 👤 Member for 21 years 10 months

I am using MSP version 2000 and it is working even though if select any specific day as non working day that also shows in bar area as band of non working day. I think it works in lower version of MSP also.

F
Forum Guest 👤 Member for 17 years 4 months

Raj,



But still the gray band in the graphics won’t move to Thu/Fri. BTW, which version are you using?

R
Raj Maurya 👤 Member for 21 years 10 months

Select Thu & Fri then make them non default working time and Sat & Sun as non working time in calander.This will change weekend as Thu & Fri as you want it.

R
Raj Maurya 👤 Member for 21 years 10 months

There is no levelled non working day band in MSP. You can edit the day you want non working that will show in bar area then you insert the text (reason of non working day) on the band. Hope this will help you to identify non working day.

F
Forum Guest 👤 Member for 17 years 4 months

I have similar problem in showing the week-ends to Thu/Fri as the gray band is fixed to Sat/Sun. Note that Thu/Fri is the week-end in Arabic countries.



proj_planner

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts