Master Projects and Sub-Projects.

F
Forum Guest 👤 Member for 17 years 6 months
W
Will Russell 👤 Member for 23 years 3 months

If you use a resource pool, a project that has only resources and no tasks and share these resources (Tools - Resource Sharing - Share Resources) between your projects then the resources should have only one histogram.



Will