How to show extended durations?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Wow, thanks man.
Problem is I have the XP version & I am new to MSProject.
Can you pls. give me instructions which tell me step-by-step how to do this?
Very much appreciated.
IT Student.
IT Student,
Try this.
Update Tasks with progress.
Check Split in progress task in Schedule Option.
Set Status Date same as Current Date in Project Information Dialogue Box.
Go to Tracking Menu, Update Project
Click reschedule uncompleted work to start after your
status date.
Regards,
Se