Task duration depends on other task
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Beste M, Dear M,
Altough were dutch, i will answer this in english. Best way to solve this problem is probably to set up a structure in which codes identify the related activities. In this way you can, after modifications to the schedule, run a macro to adjust related durations.
Its not a common solution but were both seeking new and creative alternatives, I guess!
Groeten,
Ed van der Tak
Aram Planning Consultants
The Netherlands
I am faily certain that the function you are looking for is not an inbuilt function of Microsoft Project 2000.
You could probably achieve something with a couple of milestones driven by successors with %lags and span them with a parent activity, but it would not be very elagant.
Regards
Paul E Harris
Eastwood Harris Pty Ltd