Date
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
You have to "check" the calendar for the resource assigned to your activity to see if you have any non-work periods specified for the the period of the activity.
Am I too late in replying to this one!!
Jason
The default MS Project setup to for resources to be driving.
In Tools/Options/Schedule, uncheck the box "New tasks are effort driven" & Default Task Type "Fixed Duration" (both these will stop this problem from happening with new tasks.
For existing tasks, In the Task Form for the activity, ensure the Task Type is "Fixed Duration" and the "Effort Driven" box is unchecked.
Check the Calendar for the resource assigned to your activity to see if you have any non-work periods defined for the the period of the activity.
Hopefully this will solve your problem.
Reading your query won't be enough to answer you question. Please email me your file, then after evaluating it, I'll send you my findings.
Best regards,
Se