Date

R
Raz Sawar 👤 Member for 24 years 4 months
F
Forum Guest 👤 Member for 17 years 5 months

You have to "check" the calendar for the resource assigned to your activity to see if you have any non-work periods specified for the the period of the activity.



Am I too late in replying to this one!!



Jason

C
Colin Cropley 👤 Member for 24 years 5 months

The default MS Project setup to for resources to be driving.
In Tools/Options/Schedule, uncheck the box "New tasks are effort driven" & Default Task Type "Fixed Duration" (both these will stop this problem from happening with new tasks.
For existing tasks, In the Task Form for the activity, ensure the Task Type is "Fixed Duration" and the "Effort Driven" box is unchecked.
Check the Calendar for the resource assigned to your activity to see if you have any non-work periods defined for the the period of the activity.
Hopefully this will solve your problem.

S
Se de Leon 👤 Member for 25 years 1 month

Reading your query won't be enough to answer you question. Please email me your file, then after evaluating it, I'll send you my findings.

Best regards,

Se

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts