Microsoft Project Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2009-11-16 18:41 Permalink RE: Creting a baseline in MS Project Fernando, Tools, Tracking, Save baseline (Set Baseline in MSP2k7) then display the baseline bars in the Tracking Gantt Alexandre Log in or register to post comments
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2009-11-16 18:41 Permalink RE: Creting a baseline in MS Project Fernando, Tools, Tracking, Save baseline (Set Baseline in MSP2k7) then display the baseline bars in the Tracking Gantt Alexandre
Member for
22 years 9 monthsRE: Creting a baseline in MS Project
Fernando,
Tools, Tracking, Save baseline (Set Baseline in MSP2k7)
then display the baseline bars in the Tracking Gantt
Alexandre