Dear,
I used to set in the file/ options / schedule : default start time, default end time , hours per day, hours per week , days per month at the very beginning . Then I set up different calendars for different tasks. However, some calendars may have different start time, end time hours per week with previous file/ option setting. This would come out with duration in decimal places. Please advise.
Regards,
Gary Lo
Calendars in Microssoft Project
Forum Sponsor
Top Posters
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Durations have decimals because the definition of how many hours make a day, a week or a month is set in the File > Options > Schedule.
E.g. if you've defined Hours per day as 8, and you've a 12-hour task, the duration of that task in days is 1.5 days irrespective of calendar Start & Finish times.
You are better off keeping all durations in hours or keeping all calendars with same Start & Finish times.
===
jerome
PlannersPlace.com