Calendars in Microssoft Project

L
Lo Gary 👤 Member for 16 years 4 months

Dear,



I used to set in the file/ options / schedule : default start time, default end time , hours per day, hours per week , days per month at the very beginning . Then I set up different calendars for different tasks. However, some calendars may have different start time, end time hours per week with previous file/ option setting. This would come out with duration in decimal places. Please advise.





Regards,





Gary Lo

J
Jerome Odeh 👤 Member for 22 years 5 months

Durations have decimals because the definition of how many hours make a day, a week or a month is set in the File > Options > Schedule.

E.g. if you've defined Hours per day as 8, and you've a 12-hour task, the duration of that task in days is 1.5 days irrespective of calendar Start & Finish times.

You are better off keeping all durations in hours or keeping all calendars with same Start & Finish times.

===

jerome

PlannersPlace.com

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts