Resource dependent activities

F
Frank A 👤 Member for 10 years 1 month

Hi members,

 

I am working on my first Turnaround schedule on P6 8.2. 24x7, 2 shifts schedule. I have to assign 50% of my resources in the night shift and 100% in the day shift. I tried to use Task dependent activities and creating Shifts under 'Resource Shift'

When i assign shift to my resources and click on 2, it goes back to 1 automatically. I'm not able to create a schedule with 2 shifts. Therefore I changed all my activities to 'Resource dependent' and duration type to 'Fixed duration and Units' hence calculating no of resources. I have created different calendars for my day/night crew. Everything is working perfect but I am still in doubt if client will accept it or not considering all the activities are Resource dependent.

Please let me know if I am missing some point or doing it the wrong way before i submit my schedule.

 

thanks for your time and help

 

Forum Sponsor

Top Posters

Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts