2 weeks of work, so you give them 4 weeks because you don't want to deal with possible 2nd extension- cost?

2 weeks of work, so you give them 4 weeks because you don't want to deal with possible 2nd extension- cost?  - Can you ask or expect only having to pay for 2 weeks of overhead for 4 weeks of work - for the above reason.  Would you be concerned that they agree and then address different legally?

L
Larry Rino 👤 Member for 18 years 7 months

John, without knowing your contract pricing conditions and other circumstances, it's typical that daywork rates is used for additional work and that rates includes overhead, if that so, then 2-weeks extension will be fine...

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts