Weather Delay

Member for

13 years 2 months

Hi all,

In my experience ,I think it depends on the tasks, and the construction manager who will be able to confirm whether the contractor was really forced to stop the work because of the precipitation, because sometimes the contractor can work on other tasks inside buildings.

Regards,

Mar

Member for

20 years 6 months

Im no expert in delay claims, but I do enjoy the topic of weather in scheduling!

A few things to bear in mind:

1) Weather impacts activities to different degrees, for example 0.25" of rain may impact earthworks activities to a greater degree than say internal fitout

2) Is the weather impacting the entire site or or only portions of it - particularly relevant in longer linear style projects

3) Have they already made any provisions for inclement weather, and if so, is what they're claiming greater than that amount?

 

It seems a bit far-fetched to simply claim that all rainfall caused all works to be suspended.