Extention of Time of Power Plant Project

Dear all

 

I have some problem to solve and closing the contract of my project, my project already COD long time, and the project delay maybe 394 days from the amandment contract. can i propose EOT if the contract already have certificate for COD and TOC? thanks

M
Mike Testro 👤 Member for 20 years 5 months

Hi Dwi Jaka Pratsya

Provide your claim is not time barred by the contract or local jurisdiction you can present an EoT claim at any time.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts