Engineer Not Responds EoT Claim Until the Revised Finish Date

Member for

19 years 10 months

Hi Tanveer

You will see that I have deleted some of your answer.

Do NOT say such things in an open forum.

Final warning.

Mike Testro.

Member for

19 years 10 months

Dear Mr. Tastro

Thank you for your adised.

1- Some material is to be delivered by a local authority that has not been delivered so far even the schedule of the delivery hasn’t been sent to us.

2- Some material was supposed to provide by the Employer that hasn’t been delivered to date.

3- Some of the material hasn’t been approved by the Employer so far (to date)

4- Some of the design hasn’t approved by a local authority.

There were only 30 days left to finish the project on its revised finish date when the Engineer asked for the recovery program.

Cheers - Tanveer

Member for

19 years 10 months

Hi Tanveer

Some questions first.

Is the late delivery of third party materials:

1. The Employer's problem?

and

2. The cause of the delay?

If yes to 1 & 2 then what is the point of accelerating non critical tasks.

The Engineer is allowed to ask for a recovery programme which should include a milestone for the material delivery.

0% progress on the milestone will demonstrate a rolling delay to completion and help establish your EoT.

Best regards

Mike Testro