Most people outside India do not know the value of a Crore so it would give some indication of the scale of your problem if it can be converted to US$.
A straight percentage on value is not an accurate method of valuing time related costs.
Since your contract only contains preliminaries for the structure element I would sugest that you work out the weekly value of the 5% and apply it to the whole contract period - thus avoiding any overlaps.
Member for
19 years 10 monthsHi Sankar Most people outside
Hi Sankar
Most people outside India do not know the value of a Crore so it would give some indication of the scale of your problem if it can be converted to US$.
A straight percentage on value is not an accurate method of valuing time related costs.
Since your contract only contains preliminaries for the structure element I would sugest that you work out the weekly value of the 5% and apply it to the whole contract period - thus avoiding any overlaps.
Best regards
Mike Testro