Claim Preliminaries

Dear All,

Our Contact is a Item rate Contract.Scope includes Structure ,Finishing & MEP.

Preliminaries cost is provided in the contract only for structures which is 5% of Structure Contract Value.

Now we made a claim for preliminaries  for MEP & Finishing.Calculation is based on the same percentage (5%) on Finishing & MEP Contract Value.

Is this a right logic for the claim .For example we got 1 Cr for doing safety works as a perliminaries for structural works.But actual cost came around 2 Cr .These safety features are utilising by MEP & Finishing team also .So we made a claim of additional 1 Cr as a preliminaries for MEP & Finishing Works.

 

Thansk & Regrads

Sankar Vijayan

M
Mike Testro 👤 Member for 20 years 5 months

Hi Sankar

Most people outside India do not know the value of a Crore so it would give some indication of the scale of your problem if it can be converted to US$.

A straight percentage on value is not an accurate method of valuing time related costs.

Since your contract only contains preliminaries for the structure element I would sugest that you work out the weekly value of the 5% and apply it to the whole contract period - thus avoiding any overlaps.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts