Procedure to time claim

Member for

19 years 10 months

Hi CH

It is not so much the sub-con completion date that is important but the intermediate dates when your stages interface with other contractors.

So if the RC frame is late then the M&E first fix to soffites will be delayed and/or the cladding will be late.

You must notify the main contractor of all such delays and the impact on your programme.

Best regards

Mike Testro

Member for

15 years 9 months

Hi Mike,

It is not a binding sub contract document. We do issue a programme to them, although it was never officially tracked.

We do have a subcompletion date in the contract and a main contractor master programme which states that we are supposed to carry out our works in line with the master programme. 

Thanks

CH

Member for

19 years 10 months

Hi CH

One question - is the programme a binding sub-contract document?

This advice assumes that it is not - let me know if it is and I will give you further advice.

You are on the right track - you are following the As Built v As Planned EoT method and yours is the only situation where it works.

Keep a look out for other delay events where your work progress is delayed - you will need a combination of methods in that case.

You should send in your notice of delay ASAP stating the correct contractual clauses.

Best regards

Mike Testro