Forensic Claims Analysis Member for 19 years Member for 19 years 1 month Submitted by Karthik Muruge… on Wed, 2011-09-28 06:43 Permalink Thanks Mike.. i believe as Thanks Mike.. i believe as per FIDIC its Cl 14.2 Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2011-09-22 09:56 Permalink Hi Karthik The latest Hi Karthik The latest approved programme is the basis for establishing the impact of any delay event. The same programme is used for progress reports. Best regards Mike Testro Log in or register to post comments
Member for 19 years Member for 19 years 1 month Submitted by Karthik Muruge… on Wed, 2011-09-28 06:43 Permalink Thanks Mike.. i believe as Thanks Mike.. i believe as per FIDIC its Cl 14.2
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Thu, 2011-09-22 09:56 Permalink Hi Karthik The latest Hi Karthik The latest approved programme is the basis for establishing the impact of any delay event. The same programme is used for progress reports. Best regards Mike Testro
Member for
19 yearsThanks Mike.. i believe as
Thanks Mike..
i believe as per FIDIC its Cl 14.2
Member for
19 years 10 monthsHi Karthik The latest
Hi Karthik
The latest approved programme is the basis for establishing the impact of any delay event.
The same programme is used for progress reports.
Best regards
Mike Testro