I do see the main problem right here. Been there done that. I think the main problem is the PM/engineer not cooperating. If you feel he is not respecting the contractual agreement I advise you get to arbitration (if there is a related clause) and certainly seek help from a well qualified construction lawyer.
Good Day
Roland Tannous
Member for
17 years 3 months
Member for17 years3 months
Submitted by Samer Zawaydeh on Wed, 2009-12-30 17:39
Member for
19 years 10 monthsRE: Excessive Revised Construction Drawings
Hi Raphael
Your opening sentence starts "I was involved ..."
Are you no longer part of this project?
If not then any advice will be purely acedemic.
Best regards
Mike Testro
Member for
16 yearsRE: Excessive Revised Construction Drawings
Dear all,
I do see the main problem right here. Been there done that. I think the main problem is the PM/engineer not cooperating. If you feel he is not respecting the contractual agreement I advise you get to arbitration (if there is a related clause) and certainly seek help from a well qualified construction lawyer.
Good Day
Roland Tannous
Member for
17 years 3 monthsRE: Excessive Revised Construction Drawings
Dear Raphael,
What is it that you are trying to accomplish and the other party is refusing your proposal.
If you are talking about an EOT then you need to have the proper notification as per FIDIC. The Engineer has to reply within 42 days and not 3 months.
Once you identify the problem, then we can assist you in solving it within the FIDIC clauses and conditions.
With kind regards,
Samer