28 days period

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Ahmed,



You have two running Contracts here. You are responsible for one, and very much affected by the other.



Depending on your experience and the experience of your main Contractor, you need to make sure that the Main Contractor is reporting all his delays in a timely manner withing 28 days from the start of the event, and reporting the detailed cost within 42 days (or as approved by the Engineer). Basically, the Main Contractor should have enough support and good record keeping to complete the FIDIC requirements.



On the other hand, you have your own Contract and you need to make sure that you read all the clauses carefully and check how it allows you to submit claims and get approval from the Main Contractor.



Best Regards,



Samer

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts