DESIGN AND BUILD CONTRACT

M
Mike Testro 👤 Member for 20 years 5 months

Hi Mark



I forgot to mention - please do not use captial letters in your contributions - it sounds as if you are shouting.



Best regards



Mike Testro

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear mark,



I agree with Mike, you need to check each clause in your Contract. From the time you were handed over the site and all the information provided by the Client.



Plenty or issues:

Site, permits, safety and security, cash flow, Free Issue Material, instructions of Engineer, Extras, scope change, unforeseen physical conditions.



Best Regards,



Samer

M
Mike Testro 👤 Member for 20 years 5 months

Hi Mark



Just because a contract is design and build does not preclude the usual EOT methods.



The source of the delay events may be limited to exclude late design information.



Late client changes or unforeseen circumstances may still be relevant.



Check the Contract to see what delay events are relevant to an EOT and focus on those.



Best regards



Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts