Concurrent Delay

Member for

23 years 8 months

Hi Aktham,



If I understood correctly, material has already been delivered to site and the event ended. This activity on the critical path driving the end date by 33 days.

You also said this activity is a prime cost sum; that means, this was awarded to a contractor and then novated to the main contractor. If that is the case (it is normally depends on the conditions of contract), the delay is main contractor’s responisibility as he is responsible for managing his NSC.If he was not novated, then contractor is entitled for an interim extension of time without cost, cost has to be seperately lloked at.

Member for

18 years 1 month

why is the material delivery late was the owner in any way delayed by the contractor? or was the delivery just arriving when the contractor needed it?



agree with previous post a TIA would be a good idea and definitely look at a window when just before the contractor begins their acceleration.

Member for

19 years 6 months

Thanks all for your reply; I am presenting the owner side. Although the delay in the activities from the contractor side are bigger in time, but the contractor right now is preparing a recovery program related to those activities (Contractor delay is in the Aluminum Cladding works), where they are planning to increase the manpower and accelerate the production rate to recover the delay. My question is how we should deal with this situation, when is the best time to make the analysis, and should we accept the recovery program. If so then we will end having the delivery of material as the main cause for the delay, and the contractor will get an EOT which will be used to relieve him in the future for his delays and the increase of manpower he suggest in the recovery program.

Any advice on how review this. (in the contract it is mentioned that engineer can ask for a recovery program for delayed activities which is the case in our project, where the engineer already asked for a recovery program for Aluminum Cladding works)

Member for

18 years 3 months

Dear Aktham



The method of analysis you would need to follow in order to accurately calculate the EOT and the effect of concurrent delay would be Time Impact Analysis. The SCL Protocol is a good start if you want to read around this (see http://www.eotprotocol.com). Look at guidance section 1, 1.4 Concurrency as it relates to extensions of time



Regards



Toby


Member for

18 years

Additional to reply below, to analyze which cause the delay the schedule:



- first, try to input the actual date of delivery of materials (say by Owner), then run the schedule, it will show how many days your completion date have been pushed.

- then, input the next delay (by Contractor) and apply same process, as explained above.



Notes: You can claim an EOT, only if its qualified by the conditions of the CONTRACT, because there were instances in CONTRACT that the Contractor must make some allowance to such kind risk in the CONTRACT schedule. I suggest you consult your Contract Specilist regarding that matter.



Hope these helps.

Member for

18 years 1 month

which delay is on the critical path for completion of the project? I would assume with more negative float the contractors delays are driving on the critical path but the negative float could be coming from a constraint.