VARIATIONS ISSUED AFTER THE DATE FOR PC

S
Shahzad Munawar 👤 Member for 22 years 11 months

Generally Variation Orders can only be issued prior to PC which fairly entitles you EOT and associated additional costs whereafter if such VO issues between or later date then there will be definitely an agreed extended completion date and accordingly you may entitled for EOT or Ld’s. .



In such circumstances better to seek the contractual provisions for the exact position in this case

A
ashraf alawady 👤 Member for 19 years 9 months

in my opinion and as per the condition of contract the client can issue a Variation at any time befor the date of issuing the taking over cetificate and the contractor has the right to analize the impact of this variation on the time and cost and he can get all his entitlments with the support of the condition of contract and he can prepare and submit hais claim for EOT and assoicated costs.

U
Uri Shachar 👤 Member for 23 years

Clive,



No, the Variations were issued between the approved (extended) Date for PC i.e. the date the Superintendent believed the project should have been finished and the date of PC - the date in which PC was actually achieved.



do you see a problem in that? can the Super issue a Variation after the date in which he believed the project should have been completed?



thanx



uri

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts