As-Imacted Plan is basically changed baseline. While making the original baseline, you have not thought about that particular "event" or "incident" or "activity". The As Impacted Plan is a What if plan what if you knew about that event at the time of original baseline.
As built programme - as the name suggests is record of actual events and progress. This programme progresses as the project goes ahead. Any updated programme is an as built programme up to that date.
There are various ways to calculate delay. One would be variation from baseline to as built (which is is the total delay). Variation from baseline to as impacted (delay due to particular event). etc.
Member for
20 years 8 monthsRE: Delay Analysis
As-Imacted Plan is basically changed baseline. While making the original baseline, you have not thought about that particular "event" or "incident" or "activity". The As Impacted Plan is a What if plan what if you knew about that event at the time of original baseline.
As built programme - as the name suggests is record of actual events and progress. This programme progresses as the project goes ahead. Any updated programme is an as built programme up to that date.
There are various ways to calculate delay. One would be variation from baseline to as built (which is is the total delay). Variation from baseline to as impacted (delay due to particular event). etc.