in my opnion these are all related to the lumpsum contract but when the contract on unit rate or manpower supply it is not applicable. Yes there is provision sum but it is not hard and fast that it will not increase the 25% because if the owner said that it increase form 25% and you have to complete the work the contractor will leave the job because in this case all the risk on owner shoulder not to thecontractor.
Result - The job will not complete and the loss agian toward the owner.
This rule can be applicale only in case of lumsum contrcat.
Regards
Tahir
Member for
22 years 7 months
Member for22 years7 months
Submitted by Dayanidhi Dhandapany on Sun, 2006-11-19 08:30
In FIDIC General Conditions of Contract, it has been mentioned as 15%, but in special conditons you can change it to a max of 25%. i have not yet heared anything beyond 25% so far.
Member for
19 years 8 months
Member for19 years8 months
Submitted by Ahmed Farouk on Sat, 2006-11-11 03:20
Member for
19 yearsRE: Extend of Variation Work
Dear
in my opnion these are all related to the lumpsum contract but when the contract on unit rate or manpower supply it is not applicable. Yes there is provision sum but it is not hard and fast that it will not increase the 25% because if the owner said that it increase form 25% and you have to complete the work the contractor will leave the job because in this case all the risk on owner shoulder not to thecontractor.
Result - The job will not complete and the loss agian toward the owner.
This rule can be applicale only in case of lumsum contrcat.
Regards
Tahir
Member for
22 years 7 monthsRE: Extend of Variation Work
In FIDIC General Conditions of Contract, it has been mentioned as 15%, but in special conditons you can change it to a max of 25%. i have not yet heared anything beyond 25% so far.
Member for
19 years 8 monthsRE: Extend of Variation Work
In most contracts this % is clearly stated and mostly it varies from (+/-)5% to 25%