Interim Payment / Issue date /Due date

S
Shahzad Munawar 👤 Member for 22 years 11 months

In this case, the payment due date is within 84 days from date of e submission of Invoice. Its does not matter when the Engineer issues the certificate but contractually the payment to be made to the Contractor within 84 days from the submission date. but usually the Engineer takes 21 days in certification from the date of submission and issues Interim Payment Certificate whereas remaining period relates to Employer for payment