Activities not started against scheduled

G
Giji Thomas 👤 Member for 19 years 10 months
G
Giji Thomas 👤 Member for 19 years 10 months

Hi Steeven,



This way it is correct, but some more



If compaire VARIANCE TARGET-1 Es & EF with

VARIANCE TARGET-1 LS & LF, showing all activities not started against schedule upto the data date.(Incl. float)



Filter is like:



Level-1



VARIANCE TARGET-1 EARLY START - LT- 0



Level-2



Actual Dates -WR- Project Start date to data date (update)



Level-3



%age Complete -WR - 1-99

S
Steven Oliver 👤 Member for 23 years 7 months

Depends on the software you are using.

P3 has a field "Variance Target 1 Early Start", not sure, but that may be useful.

S
Sunil Kumar 👤 Member for 21 years 2 months

Use Filter with Percent complete is equal to zero which will give you activities not started in your update.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts