Variation of Work and As Impacted schedule
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Gupta,
You have to treat each scenarios individually and incorporate into head of claims (related events that impacted on specific head of claims.
In the event that series of events continue to impact on the head of claims then what you are claiming is only interim EOT. You can also refer to the discussion "TIME AT LARGE". This is elaborated by Andrew.
Your claim may only escape you from paying liquidated damages due to continuing events that causes claims for EOT that can not be approprietely ascertain at this moment or there are still continuing events that make it imposible to finish the particular head of claims.
IMHO,
Cheers,
charlie