Collapse completed summary tasks only

D
Dariusz C 👤 Member for 7 years 6 months

Hi 

 

Is there any way to collapse summary tasks where OPC = 100% only?

My schedule contains a lot completed summary tasks so I don't want to show them in the view with entire content.

I can do this manually but looking for more convienient way.

Summary Tasks where OPC is under 100% should not be touched and be visible with all tasks underneath.

Something like below:

completedsummarytasks.png

Thanks in advance!

K
Konstantinos Parsalidis 👤 Member for 20 years 3 months

Dariusz,

You can if you make a small compromise and that is not showing the completed tasks under an incomplete summary.

The filter would be 

[[wysiwyg_imageupload:8036:]]

Criteria 1 - Summary Tasks with Task Progress Completed

Criteria 2 - Tasks or Milestones or Summary Tasks with Task Progress Specific Progress Amount Less Than 100%

Also, Objects must meet ANY criteria

Otherwise, I'm sure you could write an SQL statement but not sure I can help you with that.

Let me know if that works for you.

Kind regards,

Konstantinos

M
Mike Testro 👤 Member for 20 years 6 months

Sorry Dariusz

You have to do it manually.

One Click and save is all you need.

You don't have to show all your sub tasks.

You can have a sub summary labelledd 100% and move every complted task down into that showing only the work in prgress.

Best regards

Mike T.

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts