Overall vs Duration on Table Definition Dialog Box

A
Anu hans 👤 Member for 8 years 7 months

I have created a column for Planned Percent Complete(PPC). When I opened the Table Definition Dialogue Box under Measure of Progress I can choose on drop down following options;

Duration

Overall

Cost

I'd like to know the difference when reporting progress between duration vs Overall please?

S
Sanjib Pradhan 👤 Member for 18 years 11 months

Overall Progress :  You may wish to enter and display progress as an overall percentage complete, a measurement that is independent of the duration of a task. For example, if a task is planned to take 10 days and 5 days have elapsed but only 20% of the task work has been done, you can record that the task is 20% overall complete, even though it is 50% complete when progress is viewed as a percentage of the task duration. Changes to the actual or remaining duration will not change the overall percentage complete value. Calculating progress in this way is most useful if you do not assign resources to your tasks. This progress is similar to P6 Physical Progress.

 

Sources : Power project help

S
Sanjib Pradhan 👤 Member for 18 years 11 months

Source: Power Project Help:

You may wish to enter and display progress as an overall percentage complete,
a measurement that is independent of the duration of a task.

For example, if a task is planned to take 10 days and 5 days have elapsed but
only 20% of the task work has been done, you can record that the task is 20% overall complete, even though it is 50% complete when progress is viewed as a percentage of the task duration.

Changes to the actual or remaining duration will not change the overall percentage complete value.

Calculating progress in this way is most useful if you do not assign resources to your tasks. This progress is similar to P6 Physical Progress.

Forum Sponsor

Top Posters

Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts