Show Hammock allocation in a column at task level?

Hello,

I have a project on Asta that uses hammock tasks to summarise packages of work. I've been searching for a way to add a column that shows what hammock a task is assigned to; does anybody know if this is possible?

Any feedback would be greatly appreciated.

Thanks,

Rich

C
Charlotte Underhill 👤 Member for 9 years 11 months

Hi Richard,

You can use the parent name colun which is found under the identification category.

Hope this helps :)

M
Mike Testro 👤 Member for 20 years 5 months

Hi Richard.

Just change the code of the new task.

Best regards

Mike T.

R
Richard Mann 👤 Member for 10 years 1 month

Thanks Mike, the only problem I have with that method is if I copy a task and it copies the code to the new task even though it's not allocated to the hammock of the original task. I wasn't sure if there was any other way of showing that the new task is not allocated to a hammock without doing it manually.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Richard

Assign a code to each task and then assign the same code to the hammock.

Best regards

Mike T.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts