How to turn off annual weekly numbers

I am trying to add week numbers to the top of the programme in the date zone. I can do this this after week 52 it goes back to week 1, but I would like the week numbers to carry on as the project I am working on is over 2 years and would like the week numbers to continue.

Does anyone have any ideas how to do this, as I know it can be done, but just cant find the right option?

Thanks

N
Nathan Wharton 👤 Member for 12 years 9 months

That was exactly what I was looking for. I had Fiscal Units instead of Elapsed Units selected in the first column?

Thanks for the quick reply

R
Robert Hughes 👤 Member for 19 years 7 months

Nathan,

Right click on the date zone and select properties from the menu that opens up to open the 'Date Zone Properties' dialogue, you then need to look to the right-hand side of the 'General' tab. In the box you need to select

Type: Elapsed Units

Time Unit: Elapsed Weeks

Quantity: 1

By the sound of things you have selected 'Annual Units' instead of 'Elapased Units' in the first column. Hope that helps!

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts