Elapsed days

C
Craig Adams 👤 Member for 19 years 7 months
M
Mike Testro 👤 Member for 20 years 5 months

Hi Craig



Tasks with elapsed days are calendar day not work days.



If an ed task ends on a weekend or the middle of a holiday the next task on a workday will start on the next work day - leaving some float and therefore losing the critical path.



I only use elapsed days for a curing or drying out lead lag lead links.



If there is no real reason why the tasks should be on an ed calendar then change it to a work calendar.



Just switching the cell fortmat to work days will not solve the problem.



I have not yet discovered a work around for this small but irritating problem.



Best regards



Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts