Tasks with elapsed days are calendar day not work days.
If an ed task ends on a weekend or the middle of a holiday the next task on a workday will start on the next work day - leaving some float and therefore losing the critical path.
I only use elapsed days for a curing or drying out lead lag lead links.
If there is no real reason why the tasks should be on an ed calendar then change it to a work calendar.
Just switching the cell fortmat to work days will not solve the problem.
I have not yet discovered a work around for this small but irritating problem.
Member for
19 years 10 monthsRE: Elapsed days
Hi Craig
Tasks with elapsed days are calendar day not work days.
If an ed task ends on a weekend or the middle of a holiday the next task on a workday will start on the next work day - leaving some float and therefore losing the critical path.
I only use elapsed days for a curing or drying out lead lag lead links.
If there is no real reason why the tasks should be on an ed calendar then change it to a work calendar.
Just switching the cell fortmat to work days will not solve the problem.
I have not yet discovered a work around for this small but irritating problem.
Best regards
Mike Testro