Elapsed days

Member for

19 years 10 months

Hi Craig



Tasks with elapsed days are calendar day not work days.



If an ed task ends on a weekend or the middle of a holiday the next task on a workday will start on the next work day - leaving some float and therefore losing the critical path.



I only use elapsed days for a curing or drying out lead lag lead links.



If there is no real reason why the tasks should be on an ed calendar then change it to a work calendar.



Just switching the cell fortmat to work days will not solve the problem.



I have not yet discovered a work around for this small but irritating problem.



Best regards



Mike Testro