Project Alpha PPP (Planning Engineer / Project Controls Engineer)2006 – 2007
Provision of four Water Treatment Works for Northern Ireland, under PPP banner, with a combined output of 390 MLD. Contract Award May 2006, Contract Completion (Construction Phase) 15th October 2008. Utilising project planning techniques and identifying potential time savings indicates a potential construction completion date of 20th May 2008.
Plants are :-
Ballinrees – Turnkey Potable Water, 3 Stage Filter Plant - DAF (Dissolved Air Flotation), Primary Rapid Gravity Filters, GAC Filters (Granular Activated Carbon), Manganese Reduction Rapid Gravity Filters, Sludge Presses and all Associated Chemical Dosing. Treatment Rate 50 MLD
Castor Bay - Turnkey Potable Water, 3 Stage Filter Plant - DAF (Dissolved Air Flotation), Primary Rapid Gravity Filters, GAC Filters (Granular Activated Carbon), Manganese Reduction Rapid Gravity Filters, Sludge Presses and all Associated Chemical Dosing. Treatment Rate 140 MLD. Primary Filtration will be via modification to existing Treatment Plant assets.
Dunore Point - Turnkey Potable Water, 3 Stage Filter Plant - DAF (Dissolved Air Flotation), Primary Rapid Gravity Filters, GAC Filters (Granular Activated Carbon), Manganese Reduction Rapid Gravity Filters, Sludge Presses and all Associated Chemical Dosing. Treatment Rate 180 MLD. Primary Filtration will be via modification to existing Treatment Plant assets.
Moyola - Turnkey Potable Water, 3 Stage Filter Plant - DAF (Dissolved Air Flotation), Primary Rapid Gravity Filters, GAC Filters (Granular Activated Carbon), Manganese Reduction Rapid Gravity Filters, Sludge Presses and all Associated Chemical Dosing. Treatment Rate 30 MLD. Primary Filtration will be via modification to existing Treatment Plant assets.
Planning Software Used - Primavera P6 and Microsoft Project 2003
Provision of four Water Treatment Works for Northern Ireland, under PPP banner, with a combined output of 390 MLD. Contract Award May 2006, Contract Completion (Construction Phase) 15th October 2008. Utilising project planning techniques and identifying potential time savings indicates a potential construction completion date of 20th May 2008.
Plants are :-
Ballinrees – Turnkey Potable Water, 3 Stage Filter Plant - DAF (Dissolved Air Flotation), Primary Rapid Gravity Filters, GAC Filters (Granular Activated Carbon), Manganese Reduction Rapid Gravity Filters, Sludge Presses and all Associated Chemical Dosing. Treatment Rate 50 MLD
Castor Bay - Turnkey Potable Water, 3 Stage Filter Plant - DAF (Dissolved Air Flotation), Primary Rapid Gravity Filters, GAC Filters (Granular Activated Carbon), Manganese Reduction Rapid Gravity Filters, Sludge Presses and all Associated Chemical Dosing. Treatment Rate 140 MLD. Primary Filtration will be via modification to existing Treatment Plant assets.
Dunore Point - Turnkey Potable Water, 3 Stage Filter Plant - DAF (Dissolved Air Flotation), Primary Rapid Gravity Filters, GAC Filters (Granular Activated Carbon), Manganese Reduction Rapid Gravity Filters, Sludge Presses and all Associated Chemical Dosing. Treatment Rate 180 MLD. Primary Filtration will be via modification to existing Treatment Plant assets.
Moyola - Turnkey Potable Water, 3 Stage Filter Plant - DAF (Dissolved Air Flotation), Primary Rapid Gravity Filters, GAC Filters (Granular Activated Carbon), Manganese Reduction Rapid Gravity Filters, Sludge Presses and all Associated Chemical Dosing. Treatment Rate 30 MLD. Primary Filtration will be via modification to existing Treatment Plant assets.
Planning Software Used - Primavera P6 and Microsoft Project 2003