· Level 4 engineering WBS of Neishabour & Shariati Combined Cycle Power Plant
· Level 4 engineering time schedule of Neishabour & Shariati Combined Cycle Power Plant
· Engineering monthly report (progress tables, S-Curves & document status table of each discipline & subcontractor & Updated overall time schedule)
· Expedite document status based on critical path of project from prepare, issue to consultant, approve & issue for construction
· Check & approve engineering invoice of subcontractor