2.       Worked as Senior Planning Engineer in Cement Division at Corporate Office, Noida for 6 years for Jaypee Group(Jaiprakash Associates Limited) from Feb 2007 to Mar’2013 and is responsible for         Project Co-ordination for their upcoming Cement Plants.        I was responsible for Ø  Preparation and Updation of master Construction program iwhich includes Civil, mechanical and electrical works. Ø  Macro level planning, scheduling and monitoring for Civil Construction of various components like Preheater, Silos and Mills as well as CPP. Ø  Preparation of Capital cost Estimates. Ø  Order Finalization (including preparation of technical; and financial  comparative for offers received) for Equipments to be procured for installation at Cement Plants. Ø  Monthly progress Report for Upcoming Cement plant Projects. Ø  Co-ordination with consultants for timely release of drawings and follow-up as well as fixing of Drawings Schedule. Ø  Follow up for Equipment delivery and Supply as per the delivery schedules in the contract. 3.  Worked at Sap Labs Phase M Expansion project, Bangalore  as          Senior Planning Engineer for 1.3 years for Shapoorji Pallonji &            Company Limited (Oct’2005 to Jan’2007)                 I was responsible for Ø  Planning (Scheduling, monitoring and Resource allocation) Ø  Preparation and Updation of master Construction program Ø  Macro level planning and monitoring for every month Ø  Billing Ø  Cash flow updation Ø  Histograms Ø  MIS Report Ø  Monthly Reconciliation Ø  Monthly Labour costing for subcontractor Bills through ERP Ø  Preparation of Prestart estimate for the project Ø  Manpower Planning Ø  Preparation of Cost To complete 4.       Worked as Management Trainee at A.R Circle Flyover project,Bangalore for 9 months ,for  Simplex Concrete piles India Limited (Feb’2005 to Oct’2007)        I was responsible for Ø  Planning (Scheduling, monitoring and Resource allocation) Ø  Billing Ø  Design Coordination Ø  Quantity surveying Ø  ISO   5.Summer training at Shell Hazira LNG project for 3 months looking after        underground services  with Tecnimont ICB Pvt Ltd.  |