Exterran Planner

R
Rey Relato 👤 Member for 18 years 8 months

     Establish the overall baseline schedule in P6 with client approval for base lining.

     Update and maintain the schedule. Generate weekly forecast schedule update report and three week look-ahead construction schedule.

     Prepare weekly schedule analysis report and progress reports with S-Curves for engineering, procurement, construction and commissioning.

     Coordinate the schedule with field supervisors and sub-contractors at site providing them with information on matters related to schedule such as critical activities, delaying activities and what if scenarios.

     Coordinate with engineering and fabrication schedule engineers for the schedule update.

     Coordinate with the commissioning and operations team on matters related to the schedule.

     Liase with the client/owner’s scheduling and field engineering team on matters related to the schedule.