Fluor Daniel Consultants-Kuwait Project Controls Engineer

Project I - DOW / PIC Olefins II Project, DOW / PIC, Kuwait – USD - 3 Billion$ Project Kuwait
•     850 kta Ethane Cracker (EU2), 600 kta EO/EG Plant (EO/EG2)
•     450 kta EB/SM Plant (EBSM), 225 kta Expansion of existing Equate Polyethylene Trains
•     1,500 ton per day Oxygen Plant (Air Separation Plant - ASU2)
•     Expansion of Equate Utilities & Infrastructure (U&I)
•     New Shared Utilities & Infrastructure with Aromatics (ARO)
Responsible for coordination of all OL2K Program components, i.e. EU2, EBSM, EG2, LPK, SCT, Utilities & Infrastructure, with regards to all Planning and Scheduling related activities during the FEED, EPC and Commissioning and Start-up phase of the OL2K Program. Monitoring synchronization between OL2K Program components and 3rd parties i.e. Air Separation unit (ASU), Ethane Recovery Unit (ERU), Aromatics (KARO).