Hatch Africa Lead Planner

Sishen South Iron Ore Expansion Project (US $400 Million)



Responsible for the developing, monitoring and presenting of the following:

                              

     Major Milestone report for the project.

     Level 1 Monthly report.

     Level 2 Monthly reports.

     Level 3 Master schedule for Engineering, Procurement, Manufacturing / Fabrication, Construction & Cold/Wet Commissioning.

     Level 4 Engineering schedule (3D modelling).

     Level 4 Manufacturing & Fabrication schedules (Incl. ROS dates).

     Level 4 Construction schedules for all disciplines.

     Level 4-5 Recovery schedules for Engineering, Fabrication & Construction in areas of concern.

     Level 4 Cold/Wet Commissioning Schedules (C1-C4)

     Tender evaluations & contractual schedules for suppliers and contractors.

     Project Trends.

     S-Curves for Engineering, Procurement & Construction (measuring the EVP).

     Commodity Curves for Engineering, Fabrication & Construction.

     Histograms for Engineering, Procurement, Construction & Commissioning.

     Histograms for Camp loading.

     Resource levelling for the project.

     Productivity reports for Engineering (by discipline) & Construction (by contractor).

     Minor Milestone report for Engineering & Construction (per discipline).

     What-if scenario’s on the Master schedule and on contractor schedules.

     Assessment and approval of contractor baseline schedules.

     Extension of time assessments on contractor’s schedules.

     Forensic claim analysis on schedules.

     Progress measurement spreadsheets for Engineering, Fabrication & Construction.

     Produce risk analysis schedules.