•     Development of detailed Primavera (P3) plans

•     Monitor and update schedule to show plan ‘v’ actual

•     Develop of construction and recovery plans

•     Record the actual quantities on site work using approved drawings.

•     Provide progress periodic reports to clients, emphasizing profitability status of the Project

•     Attend and participate in all project related meetings with senior management

•     Prepare 3 weeks ‘Look Ahead Schedules’ daily quantities installed report and associated reports showing the relationship between actual, forecast and baseline plan

•     Responsible for Resource, Plant & Equipment reports (Daily, Weekly, Monthly) using pivot tables to drill down to the detail



•     Undertake daily measurement progress report showing % actual cumulative quantities ‘v’ the baseline plan

•     Using EzBusiness program to calculate the productivity by entering the job to date quantities according ‘v’ planned quantities