Fitout & Finishes

Fitout & Finishes Rates & Build Times:

Comments

R
rowstone fausto 👤 Member for 15 years

 

Wood Doors and Frames        
Door Frames and Trim        
Single Exterior    ea 3 mh/unit
Double Exterior   ea 6 mh/unit
Single Interior    ea 3 mh/unit
Double Interior    ea 4 mh/unit
Sliding Door Frame    ea 4 mh/unit
         
Doors, Fit, Hand, and Lock        
Single Exterior    ea 5 mh/unit
Double Exterior    ea 8 mh/unit
Single Interior    ea 5 mh/unit
Double Interior    ea 7 mh/unit
Screen Doors    ea 2 mh/unit
         
Metal Doors        
Single    ea 6 mh/unit
Double    ea 9 mh/unit
         
Miscellaneous Doors Complete with Trim and Hardware        
Rolling, Manual Operated    ea 29 mh/unit
Rolling, Motor Operated    ea 36 mh/unit
Sliding, Manual Operated    ea 20 mh/unit
Sliding, Motor Operated    ea 26 mh/unit
Sliding, Fire    ea 19 mh/unit
         
Garage Doors        
Wood 16' X 7'    ea 8 mh/unit
Aluminum 16' X 7'    ea 10 mh/unit
Scuttles    ea 10 mh/unit
Caulking    ft 0.005 mh/unit
         
NOTES:         
1. Includes jambs, stops, casings, and weather stripping.      
2. Does not include sills or thresholds.        
3. On wood doors, if power planes, hinge butt routers, and lock mortisers are used, use 0.75 multiplier on installation time.
         
Window Installation        
Work Element Description Unit Man-Hours Per Unit        
         
Wood Windows        
Double Hung    ea 4 mh/unit
Casement, Single    ea 4 mh/unit
Fixed, Wood Sash    ea 3 mh/unit
Jalouse    ea 2 mh/unit
Skylights    ea 8 mh/unit
         
Metal Windows Casement         
Commercial Projected    ea 2 mh/unit
Skylights    ea 2 mh/unit
Double Hung    ea 9 mh/unit
Louvers   ea 5 mh/unit
Screens    ea 2 mh/unit
Venetian Blinds    ea 2 mh/unit
Weatherstripping    ea 3 mh/unit
Caulking    ft 0.003  
         
SUGGESTED CREW SIZE: Two to six BUs        
NOTES:         
1. Installation includes drilling for fasteners, expansion shields, installing plugs, toggle bolts, blocking, hinges, locks, and other hardware.
2. For special panic device for doors add three hours for single, four hours for double doors.
         
Glass and Glazing        
Work Element Description Unit Man-Hours Per Unit        
         
Small Panels 2-FT. Square or Less    ft 0.2 mh/unit
0.19 sg.m.-   m2 1.7  
Medium Panels 2- to 6-FT Square    ft 0.2 mh/unit
0.0185-to 0.557 sq.m.   m2 1.8  
Large Panels 6- to 10-FT Square    ft 0.2 mh/unit
0.557- to 1.0 sq.m.   m2 2.3  
Plate Glass Store Fronts 200- to 400- FT Square    ft 21.0 mh/unit
18- to 37 sq.m.   m2 226.1  
         
NOTES:         
1. Estimates are based on putty set installation: if installed with metal stops and rubber, double the
man-hour figures; if vinyl set, snap-on triple man-hour figures; for insulated glass use 0.67 multiplier
2. When glazing from outside using scaffolding or swinging staging, one man is required on the ground
to support two glaziers; use 1.5 multiplier        
3. For winter work add use 1.25 multiplier.        
4. Do not air ship insulated glass units such as Thermopane, Twindow, etc., due to unequal
pressurization.