Hi, I have a very basic project with a list of milestones, all of which had baseline dates. For some milestones the baseline wasn't hit and we have later actual dates in another column. (Where there's no slip the baseline and actual columns have the same date.) I'd really like to visualize this on the gant with a baseline icon as well as the actual one so the missed milestones were easy to see. Does anyone know if it's possible to add a second date icon to the gant view like this?
Gant baseline and actual date icons for each task
Forum Sponsor
Top Posters
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
Rahmat Hidayat
32 posts
pinoyplanner
1 posts
Saqib Ullah
1 posts
Joshua,
Where you select bars, you need to create a new one that uses the BL Project Start and BL Project Finish date fields and it will display the dates from whichever project you have assigned as the "Project Baseline" in the Assign Baselines option.
Just create another milestone on Bar Style format using Actual Start and Actual Finish.