Good Day,
If i want to submit a revised program of work for a counstruction project witch is four months to finish, do i have to submit the remaining activities only or the full program??
regards,
Good Day,
If i want to submit a revised program of work for a counstruction project witch is four months to finish, do i have to submit the remaining activities only or the full program??
regards,
On the other hand keeping activities no longer within the scope of work as well as leaving the original logic in place is not best practice:
In a nutshell: activities with progress shall be kept while activities no longer within the scope of work shall be deleted from the CPM model.
you can always just filter for in progress AND not started activities to see what is remaining
Thank you all for your answers
I better submit the full program
The purpose was just to reduce the number of the activities to be easier to review.
Please be reminded that if you delete from your CPM all activities already finished it can happen that some relationships to the deleted activities may still have some remaining lag and the new model be in error. Better keep finished activities and issue a report to show only activities after DD or any selected date.
Schedule showing all activities:
The same schedule with some activities deleted might be wrong:
whats the difference what is done is done
if you do NOT have the previous actvites in the schedule then at the end you will not have a fully as-built schedule you will have bits and pieces. What if the schedule gets delayed to a virus and it stretchs out to 8 months ?
Hi Ahmed
What is the purpose of your revised programme?
Best regards Mike Testro