Hi all
I have a 30 week programme that has a 2 week shutdown over Christmas. The current week numbers in the date zone show it coming out as 32 weeks, is there any way to not show week numbers over the 2 week shutdown?
ie. up to week 5, then nothing for 2 weeks, then in January start from week 6?
Thanks in advance!
Alex
Brilliant, that worked thanks Ben!
Hi Alex,
In the Date Zone Properties (right-click within the Date Zone > Properties), the line currently representing your week numbering will likely state Type = "Elapsed Units", Time Unit = "Weeks". If you change Elapsed Units to instead be "Working Units", it will reflect your folding calendar's exceptions. You should then see the change you want in your date zone.
[[wysiwyg_imageupload:7064:]]
Best wishes,
Ben @ Powerproject