Dear All,
I'm currently working on preparaing interface and access dates document for a railway construction project,which includes viaduct,electrical track depot,rolling stock and inspection ,I'm expecting some ideologies, details to consider for preparing interface and access dates and to calculate the durations.
If possible kindly share some supporting documents related to it.
create milestones as handoff dates priior to your work starting. Make these constraint dates and get the dates from the responsible party.
So the completion of their activity is the predecessor to your work. Even if you only get a pdf file from them create a activity in your schedule as a milestone and use their activity number in YOUR schedule. This way if you only get a pdf schedule update you know what activity number to look for