Hi All,
I need some assistance in regards to displaying a two weekly programme.
Firstly, I have all non-working time showing but with a grey fill, how can this be made to go behind the subheadings?
Secondy, is there a way to specify a time period to be printed? I've managed to only have the tasks within a timesheet showing with a filter however when I go to print it seems to be fixed on printed 3-4 months as opposed to 3-4 weeks.
Thanks for your help.
Print preview
-->Print setup
-->options tab
-->Timescale Start
Timescale Finish
also look at
--> calendar icon (on)
--> View
--> timescale
--> Show Primary Dates
Calendar
Month week or what every you want it to be
-->ok