I am creating a programme to completion that will require weekend working.
I have set the calendar to 7 day working week but when I set an activity to work saturday and sunday, the activity bar jumps to the monday.
How do I prevent this from happening?
Thanks
Hi Dominic
Are you sure that you have set the calendar to 7 working days?
Also check that the calendar on your resource allocation is the same - it will over ride the plan calendar.
For instance if you have a gang of 3 carpenters - catholic - jewish and muslim - each with their own calendar you will only get 4 days work in the eek.
Best regards
Mike Testro