Total Manpower

Dear All,

, I got a project that will complete within 2-1/2 yrs with estimted manhour of 175,000 Hours, I drafted a schedule that loaded with manpower. Expert advise how much direct workers required to complete the work activity. Thanks a lot.

Regards

Ron

V
Vladimir Liberzon 👤 Member for 25 years 4 months

As was discussed before resource hours and resource quantities are not proportional.

But in any case the number of workers is not the same during the project life cycle. The number of workers at any time is determined by the project schedule.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

if you have the estimated manhours then you should know out of the 175,000 manhours how much is direct and indirect how did you come uo with this numebr in the first place ?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts