Issues in calculate the projects completion%

Hi 

 

For example, 

Project A have 2 Milestones start in 2017 and 2018

The work in milestone 1 is 100% complete , which is represent the major efoort og the whole project 

milestone 2 is actually to do FQA 

the point is the system we have consider all milestones as one weight which is not represent the reality.

 

* I can not use weghts formula because of top management order !

I need to came up with another soluation.

U
urvashi tyagi 👤 Member for 9 years

Hi Emran,

Check out PineStem(PineStem.com) Project management tool, it might be helpful for you. Here are the main features to contribute to your project success or to check the status of your project:-

1.Project planning :- Through user stories, tasks, sprint creation, sprint burndown chart, you can monitor the progress of your project and can do the proper planning of it.

2.Project status-To check the current status of the project,this tool use different reports such as Employee load graph,project load graph, which shows the current load of any employee across project and your project status too in terms of tasks load and it's status.

As i said there are different reports which suits your needs, few of them are:-

Sprint comparison report- which show the comparison of the sprint in a project and it's progress in terms of total budgeted hours, total spent hours, total number of tasks and bugs created in each sprint.Hence help you in motinoring your project progess throuhg sprints.

And  many more new reports are coming soon thereby keeping you on the top of the analysis of your project . And also helps you to moitor your project performance .

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts