Paste Linking

D
Dean Grimes 👤 Member for 9 years 3 months

Hi all

Can anyone please help me out and give me some guidance.

I would like to set up a task pool that could be linked to the main programme I.e. If I was to alter the the task pool durations or operation it would automatically alter the main programme. For example paste linking as if you would in excel.

Many thanks in advance for your help

M
Mike Testro 👤 Member for 20 years 5 months

Hi Dean

You can run a filter on a type of task - say Plaster Walls - and then make all the changes at once.

Best regards

Mike Testro

D
Dean Grimes 👤 Member for 9 years 3 months

Mike
Thank you for your prompt response.

The issue that i have is that i am having to produce a number of identical sequences of work which the client seem to be constantly changing, and as i have around 400 of these sequence patterns i am having to change them all individually.

Is there any way i can link them to one task pool so that if i change the task pool it changes all of the sequences in the bar chart. I.e. Paste linking in excel (alter 1 and it changes all the other tasks)

M
Mike Testro 👤 Member for 20 years 5 months

Hi Dean - Welcome to Planning Planet

The spreadsheet in the PowerProject table is the same format as excell. You can copy / paste between the two at any time.

I prefer Lotus 123.

Best regards

Mike T.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts