Hi,
I have the following question, on which I couldn’t find and answer in google.
How to make a task with flexible duration, which will fill the gap between other 2 tasks and will automatically adjust it’s length:
Example
Task1: Deliver building material (fix start task)
Task2: Guard delivered building material (fixed units)
Task3: Build building (fix start)
So, I want Task2 to fill the gap between task 1 and task 3. I want it to adjust it’s length depending on how late task 1 finishes. So, that it will always start when task 1 is finished, and will always finish, when task 3 starts. Is it possible with Asta?
thanks
How take make a task which fills the gap between another two task, and is automatically adjustable
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
The Hammock type activity will work if task 1 and 3 are both milestones. Add them to a hammock activity called Guard delivered building material
Hi Ben
A buffer task is infinitely flexible between the movement of the start and finish links depending on both upstream and downstream movement.
What more do you want?
Best regards
Mike T.
Hi Mike,
Making it into a buffer task will only affect the start of the buffer task depending on the movement of its predeccesor, the back end of the buffer task will have a deadline constraint applied to it. What if i want the completion of a seperate task to drive the completion of a the buffer task (with a FF link)?
So i will have two task with a gap between them. The tasks may fluctuate in terms of start/completion dates, but a seperate task linked in between them will automatically fluctuate in duration along with them, to replace the gap between the two task.
Hi Ben
Use a BUFFER task.
Creat a normal task using FS links and then Make Into> Buffer.
This is unique to Asta and does precisely what you wish.
There is an option to make it critical or not.
Best regards
Mike Testro
Hi Ben,
I would have thought Asta has "Level of Effort" type tasks......?